Dalgety - Infrapipe Limited - New Zealand

Infrapipe Case Study

Dalgety

The Dalgety Drive project involved the installation of a new private stormwater main as part of the wider drainage works at 38 Dalgety Drive, Wiri.

  1. Request a Quote
  2. Call us: 09 869 3030
  3. Email: [email protected]
  4. Office: 3 Averton Place, East Tamaki, Auckland 2013

Project Overview

The Dalgety Drive project involved the installation of a new private stormwater main as part of the wider drainage works at 38 Dalgety Drive, Wiri.

  • Approximately 95 metres of DN525 SN16 Infrapipe was installed through a shared right of way. The pipeline was laid at an approximately 1.7% grade and connected to the new private stormwater manhole, while incorporating the existing DN225 catchpit connections.

Key Project Facts

  • Location: 38 Dalgety Drive, Wiri
  • Application: Private stormwater main
  • Pipe: DN525 SN16 Infrapipe
  • Length: Approximately 95 metres.
  • Grade: Approximately 1.7%
  • Installation environment: Shared right of way / restricted access
  • Connections: New private stormwater manhole and existing DN225 catchpit connections.
Infrapipe - Auckland

Project Challenges

One of the main challenges was working within a tight, shared right of way that needed to remain operational throughout the works.

The restricted space created challenges for excavator access, trench shielding, pipe deliveries and stockpiling. The installation also required careful coordination of vehicle movements, other contractors and ongoing access through the area.

Existing catchpit connections and changes in alignment added further complexity. Custom-made bends, a junction and double couplers were required to achieve the required alignment and connections.

Products Supplied

Approximately 102 metres (17 lengths) of DN525 SN16 pipe, along with a selection of custom-made components:

  • 8 × Double Couplers
  • 2 × 45° Bends
  • 1 × Junction

Installation Efficiency

One of the key advantages was the speed of installation.

Infrapipe was supplied in approximately six-metre lengths, compared with approximately two-metre lengths for equivalent concrete pipe. This meant there were roughly one-third as many individual pipe sections to handle and install, along with considerably fewer joints.

The longer pipe lengths reduced the number of lifts required and allowed the installation team to progress more quickly along the line.

Project Feedback

Easier Handling

The team found the Infrapipe pipe considerably lighter than the equivalent concrete product. While an excavator was still used for handling, the lighter weight made the pipe easier to unload, move around the site and lower into position within the confined work area. It also made it easier to make small adjustments when setting the pipe to the correct line and grade.

Supplier Support

The support from Infrapipe was also very positive. The team was responsive when custom bends, a junction and double couplers were required, with the fittings delivered ready for installation. Having these custom components available helped keep the work moving and avoided the need for more complicated solutions onsite.

Overall Feedback

Based on their experience at Dalgety Drive, the onsite team would recommend Infrapipe and use the system again. They found the combination of longer pipe lengths, lighter weight, straightforward jointing and supplier support helped make the installation successful.

Dalgety - Infrapipe Limited - New Zealand
Dalgety - Infrapipe Limited - New Zealand
Dalgety - Infrapipe Limited - New Zealand
Dalgety - Infrapipe Limited - New Zealand
Dalgety - Infrapipe Limited - New Zealand

Contact us

  • This field is for validation purposes and should be left unchanged.

SUSTAINABLE SOLUTIONS

Our goal is to provide cost-effective products that are manufactured from recyclable materials. The manufacturing process limits waste which limits carbon impact.

Contact Us

INFRAPIPE

Infrapipe Large Pipes Projects